NAVIGATIONAL WARNING


A pipeline at the TYRA - field on position 55° 42,6' N  004° 47,8' E has been exposed.

The 200 m protection zone of the gas pipeline is temporarily expanded to 500 m around above position due to the damaged gas pipeline. The pipeline does not leak.

Within the protection zone, anchoring, dredging, boulder removal, and any use of fishing equipment operated at the seabed is prohibited.

All unauthorized traffic at the position will be rejected.

The guard vessel E95ENHIØRNINGEN, call sign OZTQ, is placed at the position and can be contacted on VHF channel 16.



ROV inspection on the HARALD field

The diving vessel EDT PROTEA will conduct ROV inspections on the HARALD field in the period from February 16 and approx. 5 days ahead.

As the work is weather dependent delays can occur both around the start time as well as with completing the job.



BUOY REMOVED AT THE REGNAR-FIELD

The buoy at the REGNAR-field, position 55° 23,123' N  005° 13,831' E, has been released and towed to a yard in Esbjerg for maintenance.

A red and black coloured isolated danger marking buoy has been placed at the position with following light characteristic: White fl(2)10s

A safety zone of 500 m is still in force on the field.


There is no guard vessel at the field anymore.




ESTABLISHMENT/RELOCATION OF RIGS

The drilling rig MAERSK RESOLVE is moved to the LUNA-1 location February 9, 2012 and is now working for NORECO.

The drilling ENSCO 71 is jacked up at the DAN FF platform.

The drilling rig ENSCO 72 is jacked up at the TYRA West C platform.

The drilling rig GSF MONARCH is jacked up at the HALFDAN HDA platform.

The drilling rig ENERGY ENDEAVOUR is jacked up at the DAN D platform.

The
accommodation platform ATLANTIC LABRADOR is jacked up at the DAN FB platform.