Thor Offshore Windfarm
The company RWE is constructing an offshore windfarm West of the Port of Thorsminde at the Westcoast of Jutland.
The vessel OLYMPIC ELECTRA is at the Thor site for a boulder clearance campaign. The vessel is presently working inside the restricted area at the Thor site.
The vessel SØLØVEN is acting as guard vessel, listening on VHF ch. 16.
The rock placing vessel SIMON STEVIN is working on the scour protection inside the restricted area at the Thor site.
The vessel MOVER will join the project March 21. She will be sailing between Thor site and Thyborøn.
From January 8, 2025 a buoyed prohibited area to be established bounded by below mentioned positions.