The company Alcatel Submarine Networks are laying a subsea cable between Denmark and UK, from Nov 2019 - September 2020 (Havhingsten subsea telecom system).

Cable installation and ploughing will be resumed by the C/S Ile de Bréhat (sister ship of C/S Ile de Batz) mid August 2020, from Denmark / UK EEZ border towards UK coast. 

C/S Ile d'Aix has left Danish waters. She is planned to perform Post Lay Burrial activities in the Danish North Sea from end of July until second half of September.